Frequently Asked Questions

If You’ve Got Questions. We’ve Got Answers!

Typically, a 250 unit property takes about 6 – 8 weeks to complete.

We use all leading U.S. manufacturers of paint.

Our labor warranties often coincide with the paint manufacture warranties depending on the products, usually between 5 and 10 years.

Yes, we provide dated schedules for all projects.

Yes, we hand deliver dated notices to all residents to all types of properties.

Yes, we make sure to leave 1-5 gallons of paint for touch up as well as a maintenance binder provided by the paint manufacturer to make ordering more paint very simple.

No, we access patios and balconies by ladder, and spray all unit doors closed.

We do not know of any permits required in any of the municipalities that we work in that need a permit for an exterior repaint, however color approval with almost all municipalities is required.

Depending on the city it can take up to 4-6 weeks for initial approval but can take up to three months if there are resubmittals.

No, if the property is in compliance and it is being painted the same color you do not need to get city color approval.

There are many reasons that a full prime may be required when repainting a property, but most all have to do with waiting to long to repaint.  Life expectancy of paint coatings in the Southwest is 7 to 10 years.

Depending on the original product used, expected useful life of an average product is 7 years in the Southwest.  Many management companies schedule their properties to be repainted every 6 to 8 years.  With high quality products that schedule can be extended to as much as 10 years.